THE FOLLOWING
ACTION STAGES MAY VARY DUE
TO:
WEATHER FORECAST
EXISTING GROUND
CONDITIONS
REPORTS OF FLOODING IN UPSTREAM
WATERSHED
*ACTION STAGE –
CITY RESPONSE
10.5 Feet Water Treatment Plant contact:
Ø Fire Department
Ø Parks & Recreation Department
Ø Utilities Director
Ø City Manager
Assignments
- Fire Department : Prepare river rescue equipment
: Advise City residents on
from Custenborder Field to City Limits – advise of rising water levels
- Parks Department : Move park equipment out of Custenborder
Field
- Utilities Department : Start Stormwater Screw Pumps on
- Water Treatment
Plant : Initiate monitoring of River Levels every
30 minutes
- City Manager : Issues Public Notice of rising river levels.
Advises residents to monitor river levels at http://www.sidneyoh.com/ website.
![]()
12.1 Feet Water Treatment Plant contact
Ø Fire Department
Ø Parks & Recreation Department
Ø Utilities Director
Ø City Manager
Assignments
- Fire
Department :
Residential Areas for Flooding
- Parks Department : Monitor Water Levels At Custenborder
Field
- Utilities Director : Email staff advising not to call River
Gauge
13.0 Feet Water Treatment Plant contact
Ø Fire Department
Ø Parks & Recreation Department
Ø Utilities Director
Ø City Manager
Assignments
- Utilities Department : Personnel start filling sand bags
- *Street Department : Personnel start filling sand bags
- *Parks Department : Personnel start filling sand bags
* Depending on staff availability
![]()
13.5 Feet Water Treatment Plant contact
Ø City Manager
Ø Call Utilities Director
Ø Police & Fire Department
Assignments
- Utilities
Department : Setup
front of
the
: Place sandbags at River Bank south of Big
Four Bridge at low spot
: Place sandbags behind church at Berger
Park on
: Initiate 24 hr monitoring of river & barriers
- Street Department : Setup Traffic Detour per attached drawing
- Parks Department : Assist Utilities and Street if available
- Wastewater Treatment
Plant : Setup sandbags around Raw Sewage Pump
Station
- Fire
Department :
Residential Areas for Flooding
14.2 Feet Water Treatment Plant contact
Ø City Manager
Ø Call Utilities Director
Ø Police & Fire Department
Assignments
Ø Supervisors Report to Fire Station #1
Ø
Non-Supervisory Personnel Report to
Ø City Staff review attached 100 yr Flood Map to determine evacuation areas
14.6 Feet Water Treatment Plant contact
Ø City Manager
Ø Call Utilities Director
Ø Police & Fire Department
River bank south of Big Four Bridges is breached
Assignments
Ø As determined by E.O.C.
![]()
18.02 Feet Water Treatment Plant contact
Ø City Manager
Ø Call Utilities Director
Ø Police & Fire Department
River breaches Jersey Barriers
Assignments
Ø As determined by E.O.C.
![]()
18.3 Feet Water Treatment Plant contact
Ø City Manager
Ø Call Utilities Director
Ø Police & Fire Department
River breaches 100 Yr Flood Wall
Assignments
Ø As determined by E.O.C.