Project Home

PHASE II

MAINTENANCE OF TRAFFIC

FAQs

PROGRESS

 

CONTACTS

Nick Miller
Project Administrator and Inspector
937-498-7244
nmiller@sceoshe.com

Public Works Director: Gary Clough
Phone:(937)-498-8141
Fax: (937)-498-8150
Email: gclough@sidneyoh.com

Randy Magoto
Engineering Manager
937-498-8717
RMagoto@sidneyoh.com

 

Progress

WEEK OF May 12th THROUGH May 18th
The following activities are scheduled:

  1. Work on replacement of sanitary laterals and installation of clean outs/inspection chambers continues. 
  2. Installation of storm sewer and inlet structures is complete for phase I (Russell Road to just south of Ruth Street).
  3. Water main testing is underway for the portion of the new main from Russell Road to Ruth Street and Sturm Construction will begin switching services over this week.
  4. Vectren Gas Subcontractor continues work on relocating gas mains and installing new gas services to businesses and residents.

***As a reminder Wapak Ave is closed to through traffic.  Local residents and businesses will maintain access from either end of the project depending on the location of the contractor and the City encourages residents to support the local businesses during this project.  A detour route for through traffic is posted along Russell Road, Main Avenue and Parkwood Street.
If any resident or business owner has any issues or special needs, please contact Nick Miller, P.E., P.S., Project Administrator at 498-7244; Randy Magoto, P.S., Engineering Manager at 498-8142 or Chad Arkenberg, Project Inspector at 498-8140.

 

WEEK OF APRIL 21st THROUGH APRIL 27th
The following activities are scheduled:

  1. Night closure of the intersection of Russell Road and Wapak Avenue from 8pm to 6am on April 22nd and 23rd are underway with Sturm Construction extending water mains and storm sewers through the intersection. 
  2. Vectren Gas Subcontractor continues work on relocating gas mains and installing new gas services to businesses and residents.
  3. On Thursday April 25th Sturm Construction will begin installing new water mains from the intersection of Russell Road north along the eastern side of Wapak Ave.
  4. Wapak Ave will be closed to through traffic beginning April 25th local residents and businesses will maintain access from either end of the project depending on the location of the contractor.  A detour route for through traffic is posted along Russell Road, Main Avenue and Parkwood Street.

If any resident or business owner has any issues or special needs, please contact Nick Miller, P.E., P.S., Project Administrator at 498-7244; Randy Magoto, P.S., Engineering Manager at 498-8142 or Chad Arkenberg, Project Inspector at 498-8140.

 

Date: 4-17-13 NOTICE OF PUBLIC MEETINGS 5:00 p.m. – 6:00 p.m.at Grace Baptist Church Parking Lot, 137 W. Edgewood

Date:  3-14-13      Bids are opened.

Date:  2-21-13      City advertises for bids. ODOT requires 22 day publicly-opened bids with 3 advertising dates. Project advertising dates: 2-21-13; 2-28-13; & 3-7-13.