PHASE II OVERVIEW
This portion of the Wapakoneta Ave Reconstruction Project
involves the widening of Wapakoneta Ave from Parkwood Street
south to Russell Rd. The new road will be three lanes with
appropriate curb/gutter, storm drainage and sidewalks.
Time Frame: Year 2013
Initiate Design Plans: 2011
Complete Design Plans: 2012
Construction: 2013
PHASE II FUNDING SOURCES
Small Cities Funds from the Ohio Department of Transportation have been granted to the City for construction in 2013, additional funds from OPWC will be requested in the fall of 2011.
WAPAKONETA AVENUE RECONSTRUCTION
Parkwood Rd to Russell Rd